Project: Henry Ford OptimEyes

 You truly held to your word when you said the savings on construction bids you would negotiate for Henry Ford OptimEyes would more than pay for your company charges.”

Client:

Henry Ford OptimEyes

 

Project:

Renovation of 25,000 SF Facility in Troy. Merged three locations into one Super Vision Center.

 

Our Roles:

Owner’s Representative

Relocation Specialist

Key Responsibilities:

Overseeing overall project budget and timing, construction and move RFP development.

 

Challenges:

Receiving timely decisions from multikey contacts within various departments to meet very aggressive project deadlines.

 

Completing project with zero client downtime to provide smooth transition to patients and retail customers.

Solution Summary:

Developed strong relationships with integral personnel.

Performed weekly cross-functional team meetings for consistent communication and timely decision making.

Maintained aggressive construction timeline, ensuring every party completed tasks prior to due dates.

Developed detailed Move Sequence to guarantee organization and timeliness of move vendor, allowing OptimEyes staff time for unpacking and space setup prior to grand opening of new facility.